Track Work Construction Scheduling using Linear Scheduling Method
dc.contributor.author | Thammasak Rujirayanyong and Paijit Pawan | en_US |
dc.date.accessioned | 2562-07-14T15:31:06Z | |
dc.date.available | 2019-07-14T15:31:06Z | |
dc.date.issued | 2562-04-26 | |
dc.description.abstract | Railway projects have been increased recently in Thailand but the scheduling method used by contractors of this kind of project was not appropriate based on the nature of activity in project . Linear scheduling method (LSM) was reviewed and applied to schedule a project case study. The case study was a conventional railways ballast track project. Data related to construction are collected such as method statement and production rate and case study of 20-kilometer day. Feedbacks and comments from contractor were positive when compared with current schedule technique used by a contractor as a project plan can be displayed distance and production rate consequently macro view and micro view of a project are provided. | en_US |
dc.identifier.citation | Paijit Pawan RSU International Research Conference 2019 Track Work Construction Scheduling using Linear Scheduling Method | en_US |
dc.identifier.uri | https://dspace.spu.ac.th/handle/123456789/6329 | |
dc.language.iso | en | en_US |
dc.publisher | RSU International Research Conference 2019 | en_US |
dc.subject | scheduling, railway, linear scheduling, track work | en_US |
dc.title | Track Work Construction Scheduling using Linear Scheduling Method | en_US |
dc.type | Article | en_US |
ไฟล์
ชุดต้นฉบับ
1 - 1 ของ 1
กำลังโหลด...
- ชื่อ:
- 190704 Track Work Construction Scheduling using Lincar Scheduling Method.pdf
- ขนาด:
- 399.73 KB
- รูปแบบ:
- Adobe Portable Document Format
มัดใบอนุญาต
1 - 1 ของ 1
ไม่มีรูปขนาดย่อ
- ชื่อ:
- license.txt
- ขนาด:
- 1.71 KB
- รูปแบบ:
- Item-specific license agreed upon to submission
- คำอธิบาย: